3. ABB Power Transmission
ALL THE NECESSARY FUNCTIONS IN ONE MODULE
KEY FUNCTIONS SEALED TYPE
EASY INSTALLATION & FAST EXCHANGEABILITY
MAIN CONCEPTSPASS
Think different, think for
performance !
5. ABB Power Transmission
All bay functions in one module
Circuit breaker
Combined disconnector/
Earthing switch
Current measurement
Voltage measurement
Introduction
6. ABB Power Transmission
The PASS M0 ratings
Rated voltage kV 72.5 123 145 170
Rated frequency Hz 50/60
Rated current A 2500
Rated breaking current kA 40/31.5
Rated making current kA 100/80
Rated BIL kV 325 550 650 750
Temperature -30*°C / + 55 °C
* -25°C with pure SF6 for 750 kV BIL
Introduction
7. ABB Power Transmission
Where are your benefits from PASS M0?
Why PASS M0?
Price Performance
Layouts
Maintenance
Availability
Transport & Installation
Benefits
8. ABB Power Transmission
More bays on less space
Simple and innovative layouts
PASS M0 solution :
You can save 50 % of space in new PASS solution.
You can double your substation on the same AIS-footprint.
You can simplify your layouts keeping the same substation
functionality.
Why PASS M0?
Your challenges in substation engineering:
9. ABB Power Transmission
High substation availability through reliable
primary and secondary equipment
Planable maintenance and higher
transparency of installed equipment
Low operating costs
PASS M0 solution :
You decrease your unavailability compared to AIS by 90%.
Your maintenance efforts for PASS are only 40 % of AIS.
You switch to maintenance on demand.
Why PASS M0?
Your challenges in substation operation:
10. ABB Power Transmission
Short installation time
More bays in less space
Simple layouts
Highly competitive product
PASS M0 solution :
Your installation effort is only 20% of AIS.
You need only 1 compared to 14 days installation time for AIS.
You can double your substation on the same AIS-footprint.
Why PASS M0?
Your challenges as contractors:
11. ABB Power Transmission
Lowest initial investiment cost
Short installation time
PASS M0 solution :
Your initial costs for PASS and AIS substations are identical.
You reduce maintenance costs by 80%.
You reduce the total installation time for HV equipment to 1 day.
Why PASS M0?
Your challenges in substation purchasing:
13. ABB Power Transmission
Legend:
circuit breaker CB current transformer CT
voltage transformer VT line L
disconnector DS earthing switch ES
PASS M0 integrates several functions in one module:
SBB diagram
Conventional AIS PASS
BB L
DS/ES CB CT/VT
DS CB DS
CT VTES
LBB
Availability
15. ABB Power Transmission
All components are arranged in one enclosure:
CB Driver
Bushing
Circuit BreakerCombined current/
voltage sensor
Combined
Disconnector/
Earthing Switch
Availability
17. ABB Power Transmission
L
Conventional AIS PASS
Legend:
circuit breaker CB current transformer CT
voltage transformer VT line L
disconnector DS earthing switch ES
BB 2
BB 1
DS/ES CB CT/VT
DS
CB DS
CT
VTES
L
DS
BB2
BB1
PASS M0 integrates several functions in one module:
DBB diagram
Availability
22. ABB Power Transmission
Combined I/U Sensor
• built-in PISA
• high accuracy and linearity
• local data processing
• optical output (no EMC
problems)
• no saturation
• no ferroresonance
• local data store for
disturbance data
Availability
23. ABB Power Transmission
• Oil free sensors:
no leakage / ageing problems
• insulating medium SF6 gas:
less solid insulation (ageing)
Further benefits:
• High accuracy
and linearity
• Large bandwidth
• No saturation
or ferroresonance
Sensors have higher availability through:
Rogowski coil
Capacitive ring
Availability
24. ABB Power Transmission
• Frequency 50Hz/60Hz
• Rated voltage range:
17.5kV/ 3 RMS…170kV/ 3 RMS
• Measurement accuracy:
• with SF6 density monitor installed:
– class 0.2% in range
80%…120% of rated voltage;
• without SF6 density monitor:
– class 1% in range
80%…120% of rated voltage.
• Frequency 50Hz/60Hz
• Rated current range:
100A....2500A
• Rated short circuit current:
40kA RMS at 50/60 Hz
(100kA/10ms, peak value).
• Measurement accuracy:
• with SF6 density monitor installed:
– class 0.2% in range
100A…2500A;
• without SF6 density monitor:
– class 1% in range 10A…2500A.
Voltage Current
Combined I/U Sensor
Availability
25. ABB Power Transmission
With PASS you decrease your unavailability compared
to AIS by 90%
minimum number of
components
all moving parts are
encapsulated
quick exchangeable
pole means
minimum down time
MTBF = 170 years
MTTR = 4 hours
proven GIS
contact system
one instead of
three motor drives
proven GIS
interrupting chamber
over 10000 chamber
into operation
mature drive
no oil
contained
SF6 or Air
instead of solid
insulation
CBDS/ES SwitchSYSTEM CP14/CT
Availability
26. ABB Power Transmission
C&P System architecture with combined I/U sensor
process bus process bus
Bay level:
Control, interlocking, line protection,
measurement and metering (option), event fault recording
Station level:
Control, event printing/plotting, alarm annuciator,
diagnostics
Process level:
PASS M0 with intelligent sensors and actuators
(PASS M0 with PISA)
Availability
27. ABB Power Transmission
C&P System architecture with conventional CT
Process level:
PASS M0 with wired interface
Bay level:
Control, interlocking, line protection,
measurement and metering (option), event fault recording
Station level:
Control, event printing/plotting, alarm annuciator,
diagnostics
Wired interfaceWired interface
Availability
28. ABB Power Transmission
AIS PASS
Long time unavailability: 23 min/y 1,4 min/y
With PASS M0 you decrease your unavailability
compared to AIS by 90 %
Single busbar arrangement
Component AIS PASS
(1/y)
MTBF
(y)
MTTR
(h)
MF
(1/y)
MTTM
(h)
(F/y)
MTBF
(y)
MTTR
(h)
MF
(1/y)
MTTM
(h)
Current Transformer 0.0005 - 8 - -
Circuit breaker 0,0068 147 48 0.16 10
Disconnector 0,0047 212 8 0.5 4
Total 0.012 73 0,0059 170 4 0.1 41
Meanings failure rate
MTBF Meantime between failure
MTTR Meantime to repair
MF Maintenance Frequency
MTTM Meantime to maintain
1
wiht spare part (w/o: 10 h)
data source: CIGRE' WG_13.06, June 1994 for AIS/CIGRE' WG_23.02 Brochure 2000 for GIS/CEA Report 93-97 for PASS bushing
Availability
29. ABB Power Transmission
SBB in transport position
fits into a standard container 20“
2500
37001950
Transport & Installation
30. ABB Power Transmission
DBB in transport position
fits into a standard container 20“
2500
45001950
Transport & Installation
31. ABB Power Transmission
transport unit
transport unit
disassembling
installation
on support
side poles
opening
operating
position
Installation on site
Transport & Installation
40. ABB Power Transmission
Conventional AIS Double BusBar
62m
86 m
space requirements:
62 m * 86 m = 5300 m2
space requirements:
27 m * 62 m=1700 m2
27m
62 m
PASS M0 Double BusBar
PASS M0 saves 70 % of space in new substations:
Double BusBar configuration : 4 line bays, 2 trafo bays, 1 coupler
Layouts
41. ABB Power Transmission
38 m
Conventional AIS Double BusBar PASS M0 Double BusBar
18 m
Double BusBar configuration: line bay comparison
Space Savings
50. ABB Power Transmission
Comparison between AIS DBB and PASS M0 DBB:
AIS DBB
Numbers of bays 7
Numbers of foundations 100 %
Required space 100 %
Unavailability 100 %
Cost comparison 100 %
7
40%
32%
30%
70%
PASS M0 DBB
Example: 4 line bays, 2 trafo bays, 1 coupler
Layouts
51. ABB Power Transmission
Comparison between AIS and PASS substation:
Gantry foundations 4 4
Busbar foundations 16 16
Equipment foundations 65 17
Cable trenches for thousands of for 18 cables
cables
Engineering 100 % < 50 %
Total effort 100 % 60 %
AIS PASS
Example: 4 line bays, 2 trafo bays, 1 coupler
Layouts
52. ABB Power Transmission
Maintenance on demand is possible through real time
monitoring of:
…with PISA or with an additional unit
• CB operating time
• drive temperature
• accumulated I2T
• contact displacement
• motor running time
• self checking devices
• SF6 density
• etc. etc.
Maintenance
53. ABB Power Transmission
PISA = Process Interface for Sensors and Actuators
• data preprocessing at the switchgear
• self-checking electronics and drives
• continuous SF6 density monitoring
... lead to condition based maintenance
The PISA allows self-supervising operations
at the switchgear:
Maintenance
54. ABB Power Transmission
The PISA functions for the circuit breaker:
Spring Charger Control
Spring
Charger
Inductive
Sensor
Maintenance
56. ABB Power Transmission
The PISA functions for the combined sensor:
Process Bus
I: Rogowsky coil,
U: Capacitive Divider
Maintenance
57. ABB Power Transmission
3 6 9 10 years
Transparency through trend analysis (example) :
Filling
pressure
First alarm
level
Blocking
pressure
Maintenance
on demand
SF6 gas density
620 kPa
600 kPa
680 kPa
550 kPa
750 kPa
Pressure
Years
Maintenance
58. ABB Power Transmission
Monitoring of Circuit Breaker: OLM
• Data acquisition unit for on-line
monitoring of HV circuit
breakers
• Date, time, temperature,
relevant data for each event
• 2 types: OLM1 (simpler) and
OLM2
• Compact: 212*210*50 mm
installed on site
• Communication with OLM-bus
(RS485, twisted pair, 115kbps)
• PC software for unit
configuration and data analysis
Monitoring & Diagnostic
59. ABB Power Transmission
Monitoring System Architecture
Travel
SF 6-Density
Temperature
Damping
Operating circuit
supervision
Spring charge time
r
Serial communication
Arc current
Stations PC
Step 2
Modem
RemotePC
Step 3
Modem
RS 485 or optical
RS 232
Laptop
Step 1
Alarm relay outputs
for conventional system
OLM
Monitoring & Diagnostic
60. ABB Power Transmission
OLM2 : monitored parameter
Date and time
Power voltage
Heater currents
SF6 gas density and temperature
Contact status (I2t)
Coil circuits, (O, C, T)
Coil currents
Number of operations
Internal and external temperatures
Motor charge time
Mechanical travel Phase current
Motor current
Monitoring & Diagnostic
61. ABB Power Transmission
Maintenance efforts for PASS M0 is only 40 % of AIS:
Scheduled inspection yes -
of all components
Scheduled maintenance yes -
of all components
Analysis of CT / VT oil yes -
Regular switching of yes -
disconnector and earthing
Cleaning of all components yes -
Greasing of drives yes -
Maintenance on demand - yes
AIS PASS
Maintenance
64. ABB Power Transmission
Life Cycle Cost for AIS and PASS M0 S/S:
EXAMPLE: RIGID "H" CONFIGURATION
0%
20%
40%
60%
80%
100%
CONVENTIONAL PASS M0
72
100
Price performance
65. ABB Power Transmission
Customer needs:
- feed energy to S/S A, B, C
- minimum space
- maximum availability on S/S B
- cost
A A1
B B1
C
Customer solution:
- conventional double busbar system
A A1 B B1 C
S/S A S/S B S/S C
S/S A S/S B S/S C
LCC (example from ) 145 kV, Generation S/S
66. ABB Power Transmission
1st Alternative solution:
- PASS M0, single busbar
A
A1
B
B1
C
A A1B B1 C
S/S A S/S B S/S CS/S A S/S B S/S C
- same functionalities
- reduced land occupation
- reduced cost
LCC (example from ) 145 kV, Generation S/S
67. ABB Power Transmission
2nd alternative solution:
- PASS M0 double circuit breaker, Single BusBar
B
A1
A
B1
C
A A1B B1 C
S/S A S/S B S/S CS/S A S/S B S/S C
- same functionalities
- further space reduction
- further cost reduction
LCC (example from ) 145 kV, Generation S/S
68. ABB Power Transmission
0.00
0.20
0.40
0.60
0.80
1.00
[h/y]
S/S A S/S B S/S C
CONV_DBB
PASS_SBB
PASS_DCB
Outage Frequency
0.00
0.02
0.04
0.06
0.08
0.10
0.12
[1/y]
S/S A S/S B S/S C
CONV_DBB
PASS_SBB
PASS_DCB
Outage Duration
Fed S/S UnavailabilityLCC (example from )
MTBF = Mean Time Between Failure
MTTR = Mean Time To Repair,
Note: The PASS concept considers the time needed for replacing the pole or of the module instead of repairing it on site
The example is referred to a double busbar bay made with conventional component and with PASS M0 DBB
In the present case only the line and transformer bay have been replaced by PASS M0. The coupling, the busbar, the voltage transformer and the cable bushing belong to the existing substation.
The module can be provided with disconnectors only
Unavailability means the outage time for the bay due to maintenance and repair
EXAMPLE REFERRED TO A SUBSTATION WITH RIGID H CONFIGURATION: COST OF THE COMPONENTS ONLY
LIFE CYCLE COST MEANS THE TOTAL COST OF OWNERSHIP AND INCLUDES THE FOLLOWING ITEMS :
- INITIAL COST FOR BUILD UP THE SUBSTATION (C&P, ENGINEERING, COMPONENTS, CIVIL WORKS, ETC)
- OPERATION & MAINTENANCE COSTS, CONSIDERING AN AVERAGE S/S LIFE OF 20 YEARS
- REPAIRING COST AS ABOVE
THE EXAMPLE IS APPLICABLE TO THIS SPECIFIC SUBSTATION;
IT WILL BE PRESENTED AT THE NEXT CIGRE' 2000.
IT IS REFERRED TO A PROPOSED S/S SOLUTION, NOT SIMPLY LIMITED TO A SALE OF COMPONENTS:
NOTE:
- CUSTOMER NEEDS means the customer's requirements listed according to the customer priorities: VERY IMPORTANT: the customer core business is to sell energy.
- CUSTOMER SOLUTION means the solution proposed by the customer, based on its experience.
ABB SOLUTION:
- SINGLE BUSBAR SYSTEM WITH PASS M0 ASSURING THE SAME FUNCTIONALITIES;
- IMPORTANT: the feeders are connected according to the need of maximum availability on S/S B; note that S/S B can experience an outage only if the bay B1 and B or both couplers experience an outage contemporary.
IInd ABB SOLUTION
The proposed solution makes use of PASS M0 double circuit breaker.
As before, the solution assures the same functionalities and a further space reduction. Also in the present case, the maximum availability results on S/S B
COMPARISON OF FEEDED SUBSTATIONS UNAVAILABILITY DUE TO CONVENTIONAL AND PASS M0 PROPOSED SOLUTIONS:
- the comparison between conventional and PASS M0 solution shows a higher S/S (A, B, C) unavailability if feeded by the conventional solution (CONV_DBB, double busbar system) in respect to PASS M0 solutions (single busbar PASS_SBB and double circuit breaker PASS_DCB).
Life Cycle Cost comparison of the customer S/S solution (CONV_DBB), and ABB proposed solutions with PASS ( PASS_SBB and PASS_DCB).
Life Cycle Cost means the total cost of ownership and includes the following items :
- initial cost for build up the substation (c&p, engineering, components, civil works, etc)
- operation & maintenance costs, considering an average s/s life of 20 years
- repairing cost and cost of power and energy interruption (1 USD/kW and 0.2 USD/kWh)